Waterfront permits in Brevard: local, state, and federal
Shoreline work in Brevard usually needs a local building permit, state environmental review when the waterway or the work requires it, and sometimes U.S. Army Corps of Engineers authorization. This guide explains each layer, what the county asks for, and what to confirm with your contractor.
The local layer
Brevard County issues a Residential Marine Construction permit for installing or replacing docks, seawalls and boat lifts in man-made bodies of water such as canals and drainage easements. Addresses inside a city use that city’s building department. Unincorporated areas such as Merritt Island use the county.
The county page lists building, general, Marine I, Marine II and residential contractors, each within their license scope, and asks for Longshore and Harbor Workers coverage for work over water. Owners acting as their own contractor apply in person.
What the county asks for
Fees and review departments are listed on the same page. Confirm the total with the county before you approve a schedule.
- Plans signed and sealed by a Florida architect or engineer.
- A plot plan with dimensional ties and turbidity barrier locations.
- A survey prepared within the last 180 days.
- A Seawall and Dock Affidavit.
- A Notice of Commencement when the job value passes the stated threshold.
The state layer
Florida DEP’s rule exempts construction, replacement and repair of seawalls and riprap in artificial waters and residential canal systems, including only the backfill needed to level land behind the wall. It also describes limited exemptions for restoring a wall damaged by a storm within the last year, with the new face no more than 18 inches waterward of the old one, and for native plantings on eroding shorelines.
Other waters follow other rules. Parts of the Indian River Lagoon and Banana River are aquatic preserves or have other designations that can add review and conditions.
The federal layer
Work in navigable waters may need authorization from the U.S. Army Corps of Engineers. Some activities qualify under general authorizations, and others need individual review. Ask your contractor which applies and whether the proposal includes the time and cost of that step.
Why lagoon projects take longer
More agencies, preserve conditions, manatee protection requirements and turbidity controls all add steps in the lagoon system. Ask for a schedule that separates permit time from construction time, and for the agency contact for each application.
Flood rules that touch shoreline projects
If a shoreline project is part of a larger improvement to a house in a flood zone, the 50 percent substantial-improvement rule may count the costs together. Ask your building department how it counts and read FEMA’s guidance for the concept.
Who files what
The independent marine contractor normally prepares and files the applications. Ask for the permit numbers when issued, and keep the approved drawings. You, as the owner, are usually responsible for the property facts the application relies on, such as the survey and ownership records.
A short checklist before you sign
Ask your contractor to answer in writing.
- Which agencies will review my project?
- Who files each application, and in whose name?
- What is the expected schedule for each?
- What conditions will apply during construction?
- What happens if an agency requests changes?
Records to keep
Keep the approved plans, permit numbers, inspection sign-offs and final close-out. Buyers, lenders and insurers sometimes ask for them, and a complete file shortens those conversations.
If you plan to sell
Buyers and lenders sometimes ask for the permits and final sign-offs for dock and wall work. Keep them together, and tell your contractor early if a sale is planned so the schedule leaves time for close-out.
Timing and sequence
Local permit review, state review and any federal review may run in parallel or in sequence, depending on the project. Ask your contractor for the order and for the longest step, and plan the start of construction around the last approval, not the first. Conditions in the approvals, such as manatee protection and turbidity control, can affect when work may begin.
Waterfront estimates
A marine proposal for your project should state wall length and height, panel material, tiebacks, permits and who handles the agencies. How waterfront estimates work. Ask how the contractor reaches the work, whether by land, barge or both, because access changes equipment and schedule. Ask also what the bid assumes about the old wall.
How a waterfront project is sequenced
- Have the wall, dock or lift inspected and findings written down.
- Compare itemized proposals that name materials, tiebacks and permits.
- Confirm who files the local, state and any federal applications.
- Schedule construction around approval conditions and weather.
- Pass the final inspection and keep the approvals and drawings.
Check the marine contractor
For this kind of project, confirm a state license on the DBPR site, ask for liability insurance and, because waterfront crews work over water, ask about USL&H or other workers’ coverage. Ask for proof of U.S. Longshore and Harbor Workers’ (USL&H) coverage and who obtains the state environmental authorization. The longer list is on the contractor checks page. Ask who holds the marine contractor license on the permit and who files each agency’s application. Keep copies of every approval with your property records.
Seawall and dock questions
Who handles all these permits?
The independent marine contractor normally prepares and files the local, state and any federal applications. Ask the contractor to list every agency, who files each application and the expected review time, and keep copies of the approvals and the approved drawings.
Do I need an engineer for a seawall permit?
The county marine permit page lists plans signed and sealed by a Florida architect or engineer. Your contractor should say whether your scope needs sealed plans, who prepares them and whether the cost is part of the proposal or billed separately.
Which agencies review lagoon projects?
Local building departments, state agencies such as Florida DEP and the St. Johns River Water Management District, and sometimes the Army Corps of Engineers. Aquatic preserves and manatee protection conditions can add steps. Your contractor should map the agencies for your parcel.
Shoreline projects this guide covers
Agency and reference pages:Brevard County Residential Marine Construction permits (accessed Nov 2026); Florida Administrative Code 62-330.051 (exempt activities) (accessed Nov 2026); FEMA substantial improvement guidance (accessed Nov 2026). General information, not legal advice; confirm with the office that covers your address.
Guide reviewed November 2026.
Send a waterfront request
Share the shoreline length and waterway in the short form and an independent local marine contractor will arrange a free inspection.